Just in case you are interested -here is the construction schedule for the summer issue of Gunmaker

The target goal is to put it in your mailbox on the first day of the appropriate season. Notice that it starts with the goal and works backwards.

 

 

 

Construction Schedule for the Summer issue of Gunmaker #196

 

June 20th first day of summer, Gunmaker is delivered to mailboxes.

 

June 11th & 12th Gunmaker drops and is mailed

 

June 2nd Printer proof is corrected and approved

 

May 28th -29th Gunmaker goes to Printer

 

May 27th proof 2 is returned to Layout

 

May26th Proof 2 comes to editor

 

May 21st. Proof 1 is returned to layout

 

May 18th Proof 1 comes to editor

 

April 10th Gunmaker files go to Layout – allows layout 30 plus day

 

April 9th – cut off for material

 

Early April  –  1st to 9th     Gather reports and latest news from officers

Final production of any graphics

Captions for photos

Final assembly of all files

Reread and proof all

 

End of March  15th – 31st     Gather material, assemble, proof,

Collect late material

 

March 1st to 15th

Primary collection of materials

Final decision about the covers

Send reminders to officers for reports

 

End of February 15th to 28th

Create organized files for departments

Experiment with possible covers